|
Contracting for Bridges at PENNDOT.
March 1998
By Heinrich O. Bonstedt, Executive Director
Prestressed Concrete Association of Pennsylvania
1042 North Thirty Eighth Street
Allentown, Pennsylvania 18104-3420
|
Background
As with most public bidding, the letting of construction contracts in Pennsylvania
has been on the basis of the lowest responsible bid in a design–bid–build environment.
In 1960 the Pennsylvania Department of Highways modified this basic concept and
started to allow contractors to bid alternate designs of their own creation on selected
projects. The Federal Highway Administration, in 1979, recognized that competition
between materials would improve quality and reduce costs; therefore, began to require
at least two designs of competing materials for bidding when federal funds above
a certain minimum were involved. Over the years, as Departments of Transportation
became familiar with the capabilities of "new" materials, the Federal
Highway Administration raised the minimum thresholds for this requirement.
During 1980, the first Special Provisions that today basically still govern the
Pennsylvania Department of Transportation’s Contractor Alternate Design, were formally
incorporated in the Department of Transportation’s construction contract. These
provisions are essentially bid-design-build, except that the Pennsylvania Department
of Transportation prepares at least one complete design for bidding. The first Contractor
Alternate Design bid in 1981 was for a steel structure. Since 1982 the Pennsylvania
Department of Transportation has routinely practiced "Contractor Alternate
Design" bidding.
Back to Top
Past Success
In 1986 the Federal Highway Administration studied the first 5 1/2 years of the
Pennsylvania Department of Transportation Contractor Alternate Design policy and
made the following findings:
• "The bridges built with contractor alternate designs still look like all
other bridges, and they all meet the same load carrying capacity with the required
factor of safety." And "… that designers and contractors have become more
adept at using existing materials and technology resulting in overall cost reductions
without compromising safety, load capacity or durability of the structure."
• Cost savings for major bridges were 10 percent and for minor bridges 7 percent.
• A change in the material used resulted; away from steel to concrete.
A subsequent study during 1992 by the Pennsylvania Department of Transportation
noticed the following:
• The frequency of Contractor Alternate Designs peaked in 1985 when 22 projects
let were Contractor Alternate Designs.
• Designers were incorporating the ideas generated through the Alternate Design
policy.
• In a competitive environment prestressed concrete bridges proved to be more economical
than steel bridges.
• Low bid bridge alternates involved all materials:
The Prestressed Concrete Association of Pennsylvania, in reviewing the results of Contractor Alternate
Designs over the years, has also noted the almost total lack of claims from such
Contractor Alternate Design projects. The bidding results of two recent projects
are illustrated and attached as Appendix A.
Back to Top
A Tool for Developing Standards
As a manufacturing industry the prestressed concrete industry is generally operating
differently than the construction industry. It must satisfy both sides of an equation:
provide what its consumers like and produce what creates a profit. Asset utilization,
production economies of scale, and the sensitivity to the issue of labor versus
material content, have a major impact on product development efforts. Another important
element in developing standards is the manufacturer’s need to manage the risks inherent
in adopting a new standard. Gradual product modification is a key to reducing the
risks of product development. The prestressed concrete producers in Pennsylvania
have utilized the Contractor Alternate Design policy as a tool to evolve the beam
standards of today.
As a result, the designer, today, can select from 29 I-beams, 15 adjacent composite
box beams 1220mm wide, 15 adjacent composite box beams 915mm wide, 15 spread box
beams 1220mm wide, or 15 spread box beams 915mm wide, to fine tune the bridge requirements
and achieve an optimum solution. This policy also allowed for the introduction and
general acceptance of high performance concrete (8,000 psi), continuous design,
bridge decks without joints, fix – fix piers, refined live load distribution and
many more.
Back to Top
Continued Opportunities
Investment in product research and product development in the United States construction
industry is notoriously low and slow. Nevertheless, new high performance materials
and designs are being developed. Practical research and development looks to have
impact in four primary areas of interest to owners and contractors:
• Lowest possible initial cost
• Speed up construction
• Increase the life-cycle performance of the structures
• Reduce the public inconvenience and impact on the environment that is necessitated
by any construction, especially in urban areas.
Yet, the worthy results of this research are even slower in being introduced as
a mainstream solution because there is no simple way to changing the mindsets of
those charged with design. It is virtually impossible to introduce new technology
generated by research unless there is an opportunity to perform a "show and
tell" demonstration. But, an essential part of a technology demonstration project
should be a requirement to establish the competitive viability for the development.
Demonstration should not occur in a non-compete environment.
The provisions for Contractor Alternate Design, while they prohibit experiments,
do allow for new developments to be introduced in a competitive environment.
Back to Top
What Makes it Work
The PennDoT commitment to seek the best-engineered solution is basically expressed
in Chapter 2 of its Design Manual. In Section 2 – Selection of Bridge Types (see
Appendix B) it states:
"Unless approved by the Chief Bridge Engineer, alternate designs by contractors
are permitted in all cases. Justification must be provided whenever alternate designs
are not allowed."
When it comes to the actual contracting, the contractor is kept in check with the
Special Provisions included in the bidding documents (see Appendix C). Part A covers
the general rules that apply, while Part B allows the specification writer, on a
case by case basis, to modify Part A or to specify additional restrictions. To aid
the specification writer PennDoT has established this checklist of items that might
be considered.
Back to Top
How it Works
• Bid advertisement by owner.
• Contractor/Supplier team procures plans.
• Contractor/Supplier team selects a design consultant to prepare design alternatives
and performs preliminary value engineering to determine best solution.
• Best solution is refined to enable computation of major quantities for bidding.
• Contractor/Supplier team prepares preliminary conceptual plans and quantities.
(For common bridges the bidding contractor requires this about one week prior to
bid.)
• Contractor performs final cost comparisons of available options.
• Contractor submits bid using the Alternate Structure block on the bid form.
• Within 6 days of the contract award the contractor submits the conceptual design
for PennDoT approval. PennDoT must review/comment/approve/reject within 24 days.
In any event, contract time will not be extended due to any delays in approval of
the alternate design concept.
• Final construction plans are prepared, for in-depth review, by PennDoT or by a
selected consultant.
• Alternate structure is constructed.
Back to Top
Obstacles to Continued Improvements and Savings
In the most recent past we have noticed a number of structures going to bid without
the provisions that allow for Contractor Alternate Design bidding. It seems that
during the environmental process, negotiations with special interest groups result
in concessions by the Department of Transportation in order to get their approvals.
Such concessions then limit the engineering options unnecessarily and increase the
cost to the public at large. The Department of Transportation will need to hold
to its expressed policy of Design Manual 4 (see Appendix B) that requires that all
engineering options be maintained in the environmental documents and that justifications
for deviations and their special approvals be well documented. Further, the Department
of Transportation must ensure that specifications do not become so proscriptive
that the introduction of new ideas is stifled.
Back to Top